SQL Server migration cutover runbook: minimal downtime, go/no-go and rollback

A target-neutral cutover runbook for moving a SQL Server database to Azure or AWS. Covers the T-minus checklist, freezing writes, final sync, switching connections, validation, go/no-go points and a tested rollback path.

Deepak Bhardwaj3 min read

Applies toMigrations to Azure SQL MI / DB, SQL on Azure VMs, Amazon RDS, EC2 using MI link, LRS, DMS, log shipping, AG or backup/restore

1. T-minus checklist

When Task
T-14 days Full rehearsal on a copy; time every step; RTO agreed with the business
T-7 Logins, users, jobs, linked servers, certificates created on the target; firewall and DNS ready
T-2 DNS TTL for the database alias lowered to 60–300 s
T-1 Replication or log shipping healthy and current; change freeze on the app; comms sent
T-0 Bridge call open; roles: cutover lead, DBA, app owner, network, testers

2. Cutover steps (with times recorded)

  1. Stop the application (or put it in maintenance mode). Stop SQL Agent jobs that write.
  2. Confirm no writes: SELECT * FROM sys.dm_exec_sessions WHERE is_user_process = 1 shows nothing from apps.
  3. Final sync, depending on the method:
    • MI link / AG: wait for synchronised, then fail over (planned, no data loss).
    • LRS / log shipping: take a final tail-log backup (BACKUP LOG ... WITH NORECOVERY keeps the source in restoring state, which protects against accidental writes), restore it, recover.
    • AWS DMS / CDC: wait for CDC latency 0, then stop the task.
    • Backup/restore: final differential or log, then restore WITH RECOVERY.
  4. Row counts and checksums on key tables (source vs target).
  5. Switch connections: update the DNS alias / connection strings / Key Vault or Secrets Manager values.
  6. Start the app against the target; enable jobs on the target.
  7. Smoke tests by app owners: login, read, write, a report, a batch job.
-- quick row count comparison (run on both sides)
SELECT s.name + '.' + t.name AS tbl, SUM(p.rows) AS rows
FROM sys.tables t JOIN sys.schemas s ON t.schema_id = s.schema_id
JOIN sys.partitions p ON t.object_id = p.object_id AND p.index_id IN (0,1)
GROUP BY s.name, t.name ORDER BY tbl;

3. Go/no-go points

Point No-go if
Before stopping the app Sync lag above the agreed limit, or a key team member missing
After final sync Row counts differ on critical tables
After smoke tests Any critical test fails and can't be fixed in 30 minutes

4. Rollback

Plan this before the night:

  • Before the app writes to the target: just point back to the source and start it. (This is why the source stays intact and read-only.)
  • After writes to the target: you need reverse sync (MI link with SQL Server 2022 supports failing back; AWS DMS can run a reverse task; otherwise export the changed data). Decide the "point of no return" time with the business.

5. After cutover

  • Hypercare for 1–2 weeks: daily performance checks, Query Store regressions (see the validation post).
  • Backups on the target verified (restore test).
  • Source kept read-only or offline for an agreed period, then decommissioned and its licences released.

Tip

Rehearse with production-sized data. The rehearsal gives you real timings, and almost always finds a missing login, job or firewall rule.